Got questions about campus construction?

Howard Wertheimer, associate vice chancellor for Facilities Services, has answers.

An overhead view of a building under construction.
Carolina is building new facilities and renovating old ones, causing a construction boom. (Rob Holliday/UNC-Chapel Hill).

UNC-Chapel Hill is undergoing a construction boom, with cranes hoisting beams for new buildings, fences securing sites being renovated, and pedestrians and cars temporarily being re-routed.

Overall, this construction is good news, as the University builds new facilities, renovates existing buildings, tackles deferred maintenance of historic buildings and improves energy efficiency, accessibility and sustainability.

Howard Wertheimer, associate vice chancellor for Facilities Services, hopes Carolina students, faculty and staff can look past the temporary inconveniences to see the value of these investments across the historic campus and the University’s commitment to the future.

“I want to be able to answer the question ‘Is this what my successors would have done?’ rather than have them asking, ‘Why did you do that?’” Wertheimer said.

Read on for his answers to questions about campus construction. For more information about individual projects, check out Facilities Services’ interactive current construction impacts map.

Why are we building new residence halls on campus?

We have an imperative to increase undergraduate enrollment. If we want to guarantee first-year students on-campus housing, we need to make sure we can accomplish that need. So we’re building two new residence halls with about 730 beds — one is called Jackson Hall — that will expand our on-campus housing for the first time in 20 years. This project will take two years to construct to get those buildings up and running.

There are other student housing projects that are part of our housing master plan that will help address our growing enrollment and the need to modernize some of our current residence halls, including the replacement of Parker and Teague and renovations to Hinton James and others. Parker and Teague are older buildings that are getting to the end of their useful life, and we’re going to replace them with new construction. We’ll be getting more beds on the site by making higher and better use of that land in the center of campus along Stadium Drive.

A photo rendering showing a tall, brick building with a green lawn and students walking around.

A photo rendering of the new Jackson Hall.

Will you also have to build new classrooms to support enrollment growth?

We continue to make progress on improving classroom utilization, as our data shows that we have the opportunity to make better use of our current classroom stock. We are also investing in renovating our existing classroom inventory to make it more supportive of modern teaching and learning. I have spent a lot of time with the registrar, representatives from the provost’s office, and other senior leaders to develop improved classroom utilization strategies to meet or exceed UNC System requirements. Improved utilization of existing physical assets is a lot less expensive than constructing new classroom buildings.

In addition to new construction, it looks like some existing buildings are getting a glow-up?

Yes, when you are responsible for the upkeep of a 200-plus year-old campus, there will always be building renovations if we are doing our jobs right!

Right now, the south wing of Phillips Hall, the part built in 1958, is closed for a major renovation, and we expect it to reopen for the fall 2027 semester. The main focus is replacing the building’s heating and cooling system, which means new ductwork, mechanical equipment and controls throughout that wing. While we’re in there, we’re also upgrading some of the lighting, building new mechanical rooms on each floor and replacing the windows. You’ll see some changes to the roof, too, including a new dormer and chimney, and a few small updates to classrooms.

In the meantime, some sidewalks around the building are closed, which means there are pedestrian detours. We understand that this can be a particular issue for people with disabilities or anyone who has trouble with longer or uneven routes, so every effort is made to ensure remaining pathways are accessible. We always appreciate the patience of our campus during these types of disruptions.

Why is Caldwell Hall closed right now?

Caldwell Hall was built in 1912, and like many of our historic buildings, it was designed long before modern accessibility standards existed. Previously, it had no elevator, so parts of the building were out of reach for anyone who couldn’t use the stairs. This project fixes that. We’re adding an elevator and a semi-enclosed stair on the west side of the building, along with an accessible restroom on the first floor. The new addition sits slightly apart from the original facade, so we can open the building up to everyone while preserving its historic character.

What are some ways Facilities Services collaborates with student organizations on these projects?

When we started replacing the roof on the Carolina Union’s northern building in August, it also became a sustainability project. Carolina’s Renewable Energy Special Projects Committee, a student group that directs the renewable energy fee every student pays, is funding new solar panels as part of the new roof. It’s the largest project that the committee has ever taken on and a good example of students putting their own money toward a more sustainable campus.

Additionally, Carolina Housing and the Facilities Services team connected the Residence Hall Association with the design team for the new residence halls. The student leaders on RHA participated in two interactive meetings where they reviewed design ideas to help shape these new buildings in ways that are important to students.

You’re repairing the steam tunnel in front of the Naval Armory along Columbia Street. Why is it so important to maintain this infrastructure?

Unfortunately, pipes don’t last forever, and it’s important that we make strategic investments in our utility infrastructure to help reduce our energy costs and subsequently, our utility bills. When steam pipes are beyond their useful life and develop cracks and holes, we are wasting a lot of energy.

We have central plants on our campus, which is a highly energy-efficient way to supply heating and cooling to our buildings, as opposed to stand-alone cooling towers and chillers. While this might cost a little bit more money up front, this investment over time has many benefits. One, over the life of the building, it reduces our energy consumption while improving energy efficiency. Two, it builds in resiliency and redundancy for the entire campus that individual stand-alone systems at each building could not provide. Should a chiller or boiler fail at our central plant, it has systems that are interconnected, which provides redundancy while helping to minimize potential downtimes in services.

Current construction on campus

New construction

Carrington Hall renewal |March 2024 to July 2027
The Carrington Hall renewal project will replace the original west wing of Carrington Hall with a new 110,000-square-foot, state-of-the-art facility.

New Jackson Residence Hall and second residence hall|August 2026 to August 2028
Site work for construction of the new north campus residence halls started Aug. 3. This project will require the closure of Cobb Drive and a portion of Paul Green Theatre Drive. The Cobb Parking Deck will remain open throughout the project. 

Bernard Chiller Plant|April 2026 to February 2028
As part of the UNC chilled water infrastructure expansion project, a new chilled water plant will be constructed at the Bernard Street site.

Renovation/Maintenance

Caldwell Hall accessibility upgrades|Fall 2025 to spring 2027
This project will add a semi-enclosed stair and elevator to the west side of the building. The project will also create an accessible restroom on the first floor. The building will be closed during construction. 

Frank Porter Graham Student Union north roof replacement|August to December 2026
Roof replacement for the northern building of the Student Union began Aug. 24. The union will remain open during construction.  

Columbia Street steam tunnel|November 2025 to August 2028
Work has begun on steam tunnel replacement along South Columbia Street. Bus stop 3437 has been temporarily relocated, and the sidewalk at the Naval Armory is closed.

House Undergraduate Library renovations|May to early 2027
The Undergraduate Library will be closed for renovations during summer and fall semester of 2026, opening in early 2027.  

Phillips Hall HVAC and window replacement|January 2026 to March 2027
The south wing of Phillips Hall will be offline for renovation until fall semester 2027. The project will replace the existing HVAC systems throughout the building’s 1958 wing, including ductwork, mechanical equipment and controls. The project will also include some lighting upgrades through the spaces, construction of new mechanical rooms on each floor, roof modifications including a new dormer and chimney, minor classroom modifications and window replacement. Sidewalk closures and pedestrian detours are in place.